Preparing for screed day: a checklist for homeowners and builders

By Ben Phillips, director · Updated · 2 min read

Short answer: before the screeding team arrives, the building should be weathertight, the insulation, membrane and edge strip laid, any underfloor heating pressure-tested, and there should be clear access and parking for the pump and deliveries. A ready site means a better floor and avoids paying for a return visit.

The building

  • Roof on, windows and external doors fitted or boarded, so rain and draughts are kept out
  • Temperature above about 5°C, and no frost forecast for the first days
  • Wet trades such as plastering finished, or planned so they do not slow drying

The floor

  • Insulation laid flat and tight, with no rocking boards
  • Membranes lapped and taped, and turned up the walls
  • Edge strip fitted to every wall, column, pipe and door frame
  • Underfloor heating pipes clipped down, filled and pressure-tested, and left under pressure
  • Door thresholds and finished floor levels agreed and marked

Access and logistics

  • Parking for the pump, and for a delivery lorry if liquid screed is being delivered
  • The hose route from the road to the room clear, with any delicate surfaces protected
  • Water supply available
  • Permits or parking suspensions arranged in controlled zones

After the pour

  • Keep the rooms closed for the first 24 to 48 hours, then ventilate steadily
  • No foot traffic until we say it is ready
  • Follow the heating start-up schedule we give you

See liquid screed, underfloor heating screed, or book a date.

Written by Ben Phillips, director of Chelmsford Floor Screeding Ltd, floor screeding contractors based in Billericay with 20+ years of experience across Essex and London. More about us.